Transfer Maintenance for new server room

Scheduled on 11/05/2019 00:00:00 Status Cancelled Estimated finish 12/05/2019 04:30:00

Dear valued customer,

Phase1: next SATURDAY at 12:00 am GMT+1 will be the "First phase" of the transfer of cabinets. The 35% of the cabinets (20 rack cabinets), will be next Saturday in the Easter holidays to avoid as much as possible affecting the activity of your business.

This transfer will only affect the COLOCATION and DEDICATED services.

The new computer room has more dimensions because they are 700 m2 diaphanous and is in the same building on the lower floor.

The interruption of each server will be approximately 30 minutes.

We have created a replica of the current room to simplify the form of the transfer, we will make the shutdown of the server manually.

Thanks for betting on SGigabit a Spanish datacenter with more future than ever.

Associated servers and services

COLOCATION AND DEDICATED.